Hoisting of tallest chimney of ADU&VDU complex plant (for which CCIEE is the main contractor) of Hengyi (Brunei) PMB Project was successfully completed on Dec.7, 2018 after 4 days of team work. The chimney is 80m tall and was divided into 4 sections (the heaviest section of 120t) to be lifted by a 600t crawler crane.